Closure and reclamation bonds
Every mine must eventually be closed and its land restored. Many jurisdictions require the owner to lodge financial security for that cost up front, which ties up capital and adds to the funding need.
2 min read
Closure is a cost at the end of the mine's life, but a reclamation bond turns part of it into money tied up at the start.
What closure covers
- Removing buildings and plant.
- Reshaping and covering waste dumps and tailings storage.
- Treating water, sometimes for many years after mining stops.
- Revegetating the land and monitoring it.
The cost depends on the size of the disturbance, the climate and, above all, the chemistry of the rock. Mines whose waste produces acid drainage can need water treatment long after closure, which makes their closure costs much higher.
How bonding works
Rules vary, but many jurisdictions require the owner to provide before disturbing the ground:
| Form | Effect on the company |
|---|---|
| Cash deposit | Capital tied up until closure is accepted |
| Bank guarantee or letter of credit | An annual fee, and it uses up borrowing capacity |
| Surety bond | An annual premium; availability depends on the insurer |
| Trust fund built up over time | Payments during the mine's life |
The amount is usually reassessed as the mine grows, and may need to cover the full cost of closure if the government had to do the work itself. Some regulators do not accept a company's own balance sheet as security.
Worked example
An invented mine expects closure to cost $40M at the end of a 15-year life.
The discounted closure cost looks small. The bond is a real cost from the start, and it adds to the money that must be raised before construction.
At each stage
At exploration, bonds cover drill pads and access tracks and are small. From the studies onward, closure cost is estimated and should be in the model. At construction, the bond becomes part of the funding package. In production, it grows with the disturbance, and a buyer of an operating mine takes on its closure liability.
What to take away
Check that the study includes a closure cost, whether the jurisdiction requires security up front, and in what form. For an older or historic site, ask who is responsible for past disturbance.
All figures are invented for illustration. This is educational material, not legal or investment advice.
Key terms
Next in this track
Reading a jurisdiction: rankings, indices and their limitsIndustry surveys and governance indices are a useful first screen for a country, but they are opinions and averages. How to use them, and what to check yourself.Related articles
- Life of mineHow long a mine produces, and how long the whole project lasts once the build years before and the closure years after are counted.Mining economics2 min read
- TollingInstead of building a processing plant, a mine can pay to process its ore at someone else's plant. Tolling suits small or early projects, with trade-offs.Mining economics2 min read
- CAPEXCapital expenditure is the money spent to build a mine before it earns anything, plus the money spent later to keep it running and expand it.Mining economics2 min read
Educational material only. Nothing here is investment advice or an offer to buy or sell any security or mineral interest.