Mining studies: PEA, PFS and FS

Three studies of rising detail turn a deposit into a mine plan with a price tag: the preliminary economic assessment, the pre-feasibility study and the feasibility study. What each contains, how far to trust it, and what it unlocks.

5 min read

On this page

A mining study puts every concept in this track together into one mine plan and one NPV. Each study is more detailed, more expensive and more trustworthy than the last.

The three studies side by side

(scoping study) (pre-feasibility) (feasibility)
PurposeIs this worth pursuing?Which way to develop it, and does it work?Should we build it, and can it be financed?
Resources usedMay include Measured and Indicated onlyMeasured and Indicated only
Declares reserves?NoYes, usually ProbableYes, Proven and Probable
Cost accuracyabout ±30–50%about ±25–30%about ±10–15%
Engineering doneConcept onlyOptions compared, one chosenDetailed design of the chosen option
Typical costabout $0.3–1.5Mabout $2–10Mabout $10–40M, more for large copper
Typical timemonthsabout a yearone to two years
Ends stage3 → 44 → 5part of the build decision

Costs and timings are indicative for a mid-size project and vary widely.

What is inside a study

Every study covers the same chapters, in more detail each time:

  • Geology and resources: the resource estimate the plan is based on.
  • Mining: open pit or underground, mining rate, a schedule of tonnes and grade by year, life of mine.
  • Processing: the flowsheet, recovery, the product and its payability.
  • Infrastructure: power, water, roads and tailings: see infrastructure spend.
  • Costs: capex, operating costs and cost of sale.
  • Environment, permitting and community: baseline data, permits required, closure.
  • Economics: a cash-flow model after government take, giving NPV, IRR and payback, with sensitivities.

The step from resources to reserves applies the : mining, processing, cost, legal, environmental and social. That is why reserves can only come from a PFS or FS. See resources versus reserves.

What each study unlocks

StudyWhat it makes possible
PEAA first valuation. Royalty buyers, strategic investors and larger equity investors can now put a number on the project.
PFSReserves. Streams, offtake talks and serious interest from mid-tier and major miners. Permitting work is scoped around the chosen plan.
FSThe build decision. Project lenders, export credit agencies and acquirers rely on it.

A feasibility study that lenders will rely on is called . That is a judgement made by lenders and their independent engineer, not a category in the reporting codes. See the typical financing path for how the funding options change at each step.

Reading the headline numbers

A study's press release leads with NPV and IRR. Before using them, check:

  • After tax or pre-tax? Only after-tax NPV reflects what owners can receive.
  • Price deck: which metal price, and how it compares with the futures curve and analysts' long-term forecasts.
  • Discount rate: 5% is common for gold, 8% for base metals: see valuing a project.
  • Share of Inferred in a PEA's mine plan. Reporting codes require a cautionary statement when Inferred resources are included, and some limit how they can be used.
  • Sensitivity tables: how much NPV falls with a 10% lower price or 10% higher capex.
  • Who wrote it: an independent engineering firm and named qualified persons, or the company itself.

Why numbers change between studies

An invented gold project, followed through all three studies:

PEAPFSFS
Tonnes in the mine plan60 Mt at 1.20 g/t, 40% Inferred48 Mt of reserves at 1.15 g/t50 Mt of reserves at 1.15 g/t
Capex$250M$300M$330M
After-tax NPV at 5%$400M$310M$290M
After-tax IRR32%25%23%
Market value at an illustrative P/NAV0.2× → about $80M0.35× → about $110M0.5× → about $145M

Three common patterns show up:

  • Tonnes drop at the PFS, because Inferred material cannot be used and not every Indicated tonne converts to a reserve.
  • Capex rises as engineering firms up and contingencies are set more honestly.
  • NPV falls, but market value rises. Each study removes uncertainty, so investors pay a higher share of a lower NPV. The multiples here are illustrative only.

A study whose NPV rises sharply from the last one deserves a close look: a higher metal price, a bigger pit or a new processing route can all be reasons, and some are sounder than others.

Red flags

  • A PEA that relies mostly on Inferred resources, especially in the early years of the plan.
  • Metal prices well above the futures curve or consensus forecasts, without a base case at lower prices.
  • No sensitivity tables, or only upside cases.
  • Recoveries not supported by testwork on representative samples.
  • A permitting timeline faster than other projects in the same jurisdiction: see permitting.
  • Capex far below comparable projects of similar size, with no clear reason.
  • A long gap since the last study, so that costs and prices are out of date.

What to take away

Know which study a number comes from before using it. A PEA shows potential, a PFS shows a plan, and an FS shows a mine that can be financed. Expect the NPV to come down and the confidence to go up as the project moves from one to the next.

All figures are invented for illustration. Accuracy ranges and costs are indicative and vary by project. This is educational material, not investment advice.