Mining studies: PEA, PFS and FS
Three studies of rising detail turn a deposit into a mine plan with a price tag: the preliminary economic assessment, the pre-feasibility study and the feasibility study. What each contains, how far to trust it, and what it unlocks.
5 min read
On this page
A mining study puts every concept in this track together into one mine plan and one NPV. Each study is more detailed, more expensive and more trustworthy than the last.
The three studies side by side
| (scoping study) | (pre-feasibility) | (feasibility) | |
|---|---|---|---|
| Purpose | Is this worth pursuing? | Which way to develop it, and does it work? | Should we build it, and can it be financed? |
| Resources used | May include | Measured and Indicated only | Measured and Indicated only |
| Declares reserves? | No | Yes, usually Probable | Yes, Proven and Probable |
| Cost accuracy | about ±30–50% | about ±25–30% | about ±10–15% |
| Engineering done | Concept only | Options compared, one chosen | Detailed design of the chosen option |
| Typical cost | about $0.3–1.5M | about $2–10M | about $10–40M, more for large copper |
| Typical time | months | about a year | one to two years |
| Ends stage | 3 → 4 | 4 → 5 | part of the build decision |
Costs and timings are indicative for a mid-size project and vary widely.
What is inside a study
Every study covers the same chapters, in more detail each time:
- Geology and resources: the resource estimate the plan is based on.
- Mining: open pit or underground, mining rate, a schedule of tonnes and grade by year, life of mine.
- Processing: the flowsheet, recovery, the product and its payability.
- Infrastructure: power, water, roads and tailings: see infrastructure spend.
- Costs: capex, operating costs and cost of sale.
- Environment, permitting and community: baseline data, permits required, closure.
- Economics: a cash-flow model after government take, giving NPV, IRR and payback, with sensitivities.
The step from resources to reserves applies the : mining, processing, cost, legal, environmental and social. That is why reserves can only come from a PFS or FS. See resources versus reserves.
What each study unlocks
| Study | What it makes possible |
|---|---|
| PEA | A first valuation. Royalty buyers, strategic investors and larger equity investors can now put a number on the project. |
| PFS | Reserves. Streams, offtake talks and serious interest from mid-tier and major miners. Permitting work is scoped around the chosen plan. |
| FS | The build decision. Project lenders, export credit agencies and acquirers rely on it. |
A feasibility study that lenders will rely on is called . That is a judgement made by lenders and their independent engineer, not a category in the reporting codes. See the typical financing path for how the funding options change at each step.
Reading the headline numbers
A study's press release leads with NPV and IRR. Before using them, check:
- After tax or pre-tax? Only after-tax NPV reflects what owners can receive.
- Price deck: which metal price, and how it compares with the futures curve and analysts' long-term forecasts.
- Discount rate: 5% is common for gold, 8% for base metals: see valuing a project.
- Share of Inferred in a PEA's mine plan. Reporting codes require a cautionary statement when Inferred resources are included, and some limit how they can be used.
- Sensitivity tables: how much NPV falls with a 10% lower price or 10% higher capex.
- Who wrote it: an independent engineering firm and named qualified persons, or the company itself.
Why numbers change between studies
An invented gold project, followed through all three studies:
| PEA | PFS | FS | |
|---|---|---|---|
| Tonnes in the mine plan | 60 Mt at 1.20 g/t, 40% Inferred | 48 Mt of reserves at 1.15 g/t | 50 Mt of reserves at 1.15 g/t |
| Capex | $250M | $300M | $330M |
| After-tax NPV at 5% | $400M | $310M | $290M |
| After-tax IRR | 32% | 25% | 23% |
| Market value at an illustrative P/NAV | 0.2× → about $80M | 0.35× → about $110M | 0.5× → about $145M |
Three common patterns show up:
- Tonnes drop at the PFS, because Inferred material cannot be used and not every Indicated tonne converts to a reserve.
- Capex rises as engineering firms up and contingencies are set more honestly.
- NPV falls, but market value rises. Each study removes uncertainty, so investors pay a higher share of a lower NPV. The multiples here are illustrative only.
A study whose NPV rises sharply from the last one deserves a close look: a higher metal price, a bigger pit or a new processing route can all be reasons, and some are sounder than others.
Red flags
- A PEA that relies mostly on Inferred resources, especially in the early years of the plan.
- Metal prices well above the futures curve or consensus forecasts, without a base case at lower prices.
- No sensitivity tables, or only upside cases.
- Recoveries not supported by testwork on representative samples.
- A permitting timeline faster than other projects in the same jurisdiction: see permitting.
- Capex far below comparable projects of similar size, with no clear reason.
- A long gap since the last study, so that costs and prices are out of date.
What to take away
Know which study a number comes from before using it. A PEA shows potential, a PFS shows a plan, and an FS shows a mine that can be financed. Expect the NPV to come down and the confidence to go up as the project moves from one to the next.
All figures are invented for illustration. Accuracy ranges and costs are indicative and vary by project. This is educational material, not investment advice.
Key terms
Next in this track
You have reached the end of this track.
Related articles
- Why most projects fail: odds and the Lassonde curveOnly about 1 in 1,000 prospects becomes a mine. Where projects drop out, why, and how a project's value tends to rise, slump and rise again on the way to production.The junior mining world4 min read
- Resources and reservesResources measure what is in the ground and how confidently. Reserves are the part that a study shows can be mined at a profit.Exploration2 min read
- Why the funding gap existsBetween a first resource and a pre-feasibility study, projects fall between two kinds of capital: speculative money that wants discoveries and development money that wants reserves. Why the gap opens, what it costs, and who fills it.The junior mining world4 min read
Educational material only. Nothing here is investment advice or an offer to buy or sell any security or mineral interest.